About the project

The redevelopment of the Nepean Hospital is a multi-stage project. The NSW Government committed $550 million to deliver Stage 1 and $450 million to deliver Stage 2. This will also include the construction of a $26 million multi-storey car park on Barber Avenue to support the expanded services on campus.

Project Date:
Project Location:
Project Services:

The Task

Drafting Solutions was engaged to model the wet fire pipework for this project.

The Challenge

At the time Drafting Solutions was engaged, a fire contractor had not yet been awarded a contract. Drafting Solutions was engaged directly by the builder to help fast-track the modelling process.

The Solution

Drafting Solutions worked closely with the builder and the other service contractors to ensure the modelling was accurate and coordinated. We then completed a staged handover with the fire contractor when the contract was awarded.